An engineering study commissioned by the Department of Land and Natural Resources Division of Boating and Ocean Recreation (DOBOR) finds that it would be “very expensive and full of uncertainties associated with sand movement and costal processes continuing in and around Pohoiki Bay,” a June 10, 2019, DLNR press release said.

While it’s technically possible to remove sand and create a channel to the Pohoiki Small Boat Ramp on Hawai‘i Island’s lower Puna coast, the study recommended construction of a new one.

The ramp was closed shortly after Kīlauea began erupting in May 2018 and eventually became land-locked by what is now a 200-foot-wide, black sand and cobblestone beach.

Representatives from Sea Engineering Inc. visited Pohoiki on May 1 and then produced a 32-page-long report which states, “The recent volcanic activity and lava flow has resulted in the formation of hundreds of thousands of cubic yards of black sand and cobbles at the lava-ocean interface, which has been carried southward by coastal currents and now completely fills Pohoiki Bay, rendering the existing Pohoiki boat ramp land-locked and useless.”

ARTICLE CONTINUES BELOW AD
ARTICLE CONTINUES BELOW AD

Ed Underwood, DOBOR administrator, said the engineering study also revealed, “Constructing a new ramp at an alternate site would be a more straightforward project, however the rocky sea cliff Puna coastline provides few ideal locations.”

He added that seismic and volcanic activity are also concerns “virtually anywhere along this coast.”

The alternate site evaluated in this study, Mālama Flats, is just south of McKenzie State Recreation Area), and appears to offer reasonable conditions for design of an inland excavated ramp facility.

Aerial view of Pohoiki on Friday, Aug. 31, 2018. Click to enlarge. PC: USGS

“However, no quantitative site information is presently available,” Underwood said. “The ramp alternative as presented is basically a generic ramp design placed on the Mālama Flats topography. Estimated construction costs are considered representative for this type of ramp facility.”

ARTICLE CONTINUES BELOW AD

The engineering study found that no matter where the state builds a ramp along the lower Puna Coast, it will be challenging.

Engineers studied an area extending approximately 10 miles south from Pohoiki Bay to Kalapana, where the coast road turns inland.

The report found “The shoreline is almost entirely rocky sea cliffs, with deep water close to shore and relatively high (20 to 30 feet) nearshore ground elevations. There are no shallow water embayments or significant headlands to provide natural wave protection. The coast is directly exposed to the persistent prevailing trade wind generated seas. Tropical storms and hurricanes passing south of the island generate large waves that can batter the coast.”

Pohoiki Small Boat Ramp, March 2019. PC: BIN

In order to reopen the Pohoiki Boat Ramp, a channel would have to be excavated through the new beach and maintained open by shore-perpendicular jetties. Given the continuing production of volcanic sand, and the dynamic and variable waves and currents along the coast, a jetty on both sides of the channel is considered necessary to insure the continued navigability of a channel through the beach. Sea Engineering estimates it would cost approximately $37.9 million to restore the Pohoiki ramp.

ARTICLE CONTINUES BELOW AD

The estimated cost for a new facility at Mālama Flats is estimated at $14.5 million and would include:

  • A 295-foot long, 100-foot wide, and 6-foot deep entrance channel excavated inland.
  • A 0.6 acre launching and turning basin, 6 feet deep.
  • 830 linear feet of rock wave absorber along the entrance channel and basin.
  • A single lane concrete boat launch ramp, 18 feet wide and 128 feet long.
  • A 24-foot wide, 60-foot long concrete ramp approach pad. • A 30-foot long, 5-foot wide concrete loading dock, complete with fenders and mooring hardware.
  • A 100-foot long, 5-foot wide, ADA compliant loading dock approach walkway.
  • Approximately 1,330 linear feet of lava rock (CRM) retaining wall, 2 to 4 feet high, to permit raising the ground elevation in the ramp vicinity.
  • Material excavated from the channel and basin would be used as compacted fill to create a uniform +10-foot elevation backshore support area. This is necessary to prevent occasional flooding of the ramp facility by wave runup.
  • A two-lane, 24-foot wide, asphalt access roadway approximately 680 feet long.

DOBOR will need to work with the Federal Emergency Management Agency (FEMA) to secure appropriate funding to build a new ramp and associated facilities and when and if that happens will have to obtain appropriate permits and hold public hearings or informational meetings with local boaters and the community.

Sponsored Content

Subscribe to our Newsletter

Stay in-the-know with daily or weekly
headlines delivered straight to your inbox.
Cancel
×

Comments

This comments section is a public community forum for the purpose of free expression. Although Big Island Now encourages respectful communication only, some content may be considered offensive. Please view at your own discretion. View Comments