Public feedback is sought by the state as officials look at new design options under a long-term master plan to phase out the temporary wooden portables on the historic Hōlualoa Elementary School campus.

On Monday, the Hawai‘i Department of Education stated three design options were shared at a community meeting at the school, which sits at an elevation of approximately 1,400 feet above sea level. The campus was originally opened in the 1890s and serves approximately 432 students in grades pre-K to 5.

Feedback is being sought through the end of October and can be submitted online here.

The master plan was pursued after roadway speed issues and the buildout of wooden portables on the opposite side of a road and utility easement from the main part of campus created safety concerns for students. The easement provides access to residential parcels mauka of the school.

The intent of the master plan is to map out the phased construction of replacement facilities for the school’s portable structures and to address the road and utility easement running through the campus. Given the challenges around securing funding for HIDOE school projects statewide, the master plan will address the most critical issues within two phases of construction.

ARTICLE CONTINUES BELOW AD
ARTICLE CONTINUES BELOW AD

The three design options layout different campus configurations but all are designed to: create permanent classroom spaces and traditional school resources such as a library, administration building and specialty classrooms; alleviate traffic queuing from the highway fronting the school by creating designated space on the campus for drop-off and pick-up; and remove safety concerns from the road and utility easement that currently runs through the existing campus.

Option 1 (Design 4)

Screenshot

Builds a new one-story classroom building for upper grades (2-5) featuring 22 permanent classrooms in the first phase. Future phases would include constructing a two-story administration building and two-story classroom building for lower grades (K-1) featuring 12 classrooms along with removing existing wood portable structures. The campus buildings would be shifted away from the existing road and utility easement, with a designated separate entry and exit point, and a new parking lot as an added buffer.

Option 2 (Design 5A)

Screenshot

Builds a new two-story classroom building for upper grades featuring 18 classrooms in the first phase. Future phases would include constructing a new two-story administration building with a library space, a two-story classroom building for lower grades (there would be a physical connection between the two classroom buildings) and removing existing wood portable structures. This design does not include a separate entry and exit point for the existing road and utility easement, which designers said was intentional in the event the needed approvals cannot be secured.

Option 3 (Design 5B)

Screenshot

Similar to Option 2, builds a new two-story classroom building for upper grades featuring 18 classrooms but with a library space. Future phases would include constructing a new two-story administration/library/computer building and a two-story classroom building for lower grades featuring 12 classrooms, as well as removing existing wood portable structures. Similar to Option 1, the campus buildings would be shifted away from the existing road and utility easement, with a separate entry and exit point.

ARTICLE CONTINUES BELOW AD

Kanako Furchi of Design Partners, Inc. presented the design options at the community meeting and said that while the three designs vary, there is a possibility of “mixing and matching” features among the three designs. Architects for the project said the designs would be respectful and blend into the natural beauty of the area, but have modern features.

Monday’s presentation was followed by breakout sessions where attendees could provide comments on each of the design options, and rank their preferences.

The master plan will determine a preferred master plan option. The design team for the first phase of the campus improvements will complete an Environmental Assessment (EA) based on the preferred master plan option, and complete further design, engineering and technical evaluation before completing the design for Phase 1.

The EA process will include another community presentation of the updated design and environmental impacts.

ARTICLE CONTINUES BELOW AD

Once a preferred base design is selected, it could take approximately three years to complete the design and seek the needed permits. From there, the department would seek legislative funding to put the project out for bid.

View a recording of the presentation portion of the Sept. 16 meeting here.

View the slide presentation from the Sept. 16 meeting here.

Sponsored Content

Subscribe to our Newsletter

Stay in-the-know with daily or weekly
headlines delivered straight to your inbox.
Cancel
×

Comments

This comments section is a public community forum for the purpose of free expression. Although Big Island Now encourages respectful communication only, some content may be considered offensive. Please view at your own discretion. View Comments