Hawaiian Electric Begins Next Stage of Renewable Energy Procurement

Play
Listen to this Article
3 minutes
Loading Audio... Article will play after ad...
Playing in :00
A
A
A

To help meet the state of Hawai‘i’s clean energy and decarbonization goals, Hawaiian Electric recently filed a draft Request for Proposals for the third stage of its renewable energy procurement for Hawai‘i Island.

Based on recommendations from the Hawai‘i Island Near-Term Grid Needs Assessment report completed in July, the company is seeking proposals to acquire energy and capacity situated on the eastern portion of Hawai‘i Island. The company is seeking a variety of sources including new renewable dispatchable generation projects (with or without energy storage systems), extensions of existing resources after their current contract terms, standalone energy storage projects, and aggregated customer-sited distributed energy resources projects. 

Hawaiian Electric will evaluate the proposals submitted in the RFP to determine if other services ancillary to the energy target can be acquired, including regulating reserve.

Hawaiian Electric will host a virtual community meeting to discuss the RFPon Thursday, Oct. 28, at 5:30 p.m. The community is invited to tune in live on Nā Leo TV channel 54, online at naleo.tv/channel-54/, and on Hawaiian Electric’s Facebook page. Participants are welcome to ask questions during the meeting. Questions also can be sent in advance to [email protected]. The virtual event will be recorded. For more information, visit www.hawaiianelectric.com/communitymeetings.

ARTICLE CONTINUES BELOW AD
ARTICLE CONTINUES BELOW AD

“Community engagement is important as we work together to shape our island’s energy future,” said Jennifer Zelko-Schlueter, Hawaiian Electric’s Director of Government and Community Affairs on Hawai‘i Island. “We value your input and encourage you to get involved and lend your voice to these important conversations about projects that may impact you. A community meeting allows you to learn more about a project, ask questions, and understand energy policy and process. It also gives us an opportunity to understand your perspective and listen to your ideas about solutions that are inclusive and fair.”

In 2019, Hawaiian Electric began Hawai‘i’s largest procurement effort for renewable energy resources to end the use of coal and reduce reliance on imported oil for power generation. The company sought approximately 900 megawatts – up to 203 MW on Hawai‘i Island – of new renewables or renewables paired with storage. It was among the largest single renewable energy procurements undertaken by a U.S. utility.

In the first two phases, three solar-plus-storage projects and one standalone storage project totaling approximately 132 MW of generation and 492 MWh of storage were selected for Hawai‘i Island.

ARTICLE CONTINUES BELOW AD

Upon approval by the Commission, this third phase of renewable energy procurement will be opened to bids from developers locally and globally. Pending approval, the first projects are expected to come online no later than 2030. The proposed timeline for proposals, subject to Commission approval, is:

EventDate
Final RFP is issuedFebruary 14, 2022
Proposal due dateMay 17, 2022
Company selects priority listAugust 1, 2022
Best and final offers dueAugust 8, 2022
Final award group namedNovember 21, 2022
Contract negotiations beginNovember 28, 2022

Hawaiian Electric exceeded the state milestone of 30% of electricity sales coming from renewable sources in 2020, with Hawai‘i Island recording a renewable portfolio standard of 43.4%. In 2021, the percentage is expected to increase as Puna Geothermal Venture is back online and more customers are adopting rooftop solar.

Sponsored Content

Subscribe to our Newsletter

Stay in-the-know with daily or weekly
headlines delivered straight to your inbox.
Cancel
×

Comments

This comments section is a public community forum for the purpose of free expression. Although Big Island Now encourages respectful communication only, some content may be considered offensive. Please view at your own discretion. View Comments